- X Do we want to increase sampling rate from 5Hz to 10Hz or 20Hz on the sonic anemometer?
- 10Hz is standard for flux measurements according to Joe MacFaddon of UCSB.
 
 - Heated Sonic Anemometer?
- Probably not really necessary until someone is gonna be actively using turbulent calc's during those times.
 - No action on this for 2012.
 
 
Notes
- 20120904.10:34 down clear radiometer swapped out.
 
New Stuff
- Solid state mux?
- Kerry to order and ship out this fall.
 
 - Green LiDAR?
- Doubtful and the current LiDAR should be fine for another season as is.
 
 - Snow Pillow from Gherke.
- Need to call Frank.
 
 - ?MASC needs? (Ned)
 
Replace/Rebuild/Reinstall/Recalibrate
- X radiometers: Done on 20120904.
 - Depth pingers: Replaced Cambell on 20120904 or 05, Judds seem fine.
- ! Kerry will calibrate and send spares back to CUES this fall.
 
 - ! Sutron: Email to vendor on 20120907.
 - ! Anemometers: replaced wind vane, Kerry to service spare and return to CUES.
 - LiDAR
- Doesn't need updating, stored in bunker, re-deploy before first storm.
 
 - Soil moisture probe replacement.
- ! Kerry to ship calibrated probes to Alex.
 
 -  ! Lysimeter tipping bucket overhaul (MTC): ideally put them side by side in a single row and down low, close to floor.
- Drains are 1.5"
 - Do something to accommodate 3/4" chimney drain on South Wall.
 - North Wall: 30"x30"x6"ish (2 drains at 2.5", 2 @ 2")
 - South Wall: 30"wide x 24"tall x 6"ish deep. (all 4 drains @ 2")
 
 - X Redo cable pulls w/ wire.
- West wall still needs loop built into end in bunker.
 
 - X Recoil DTS cable.
- Took full photo inventory and sketched a map of layers and markers.
 
 -  ! Snow thermister deployment protocol.
- Alex or Ned will deploy Thermisters prior to significant storms.
 
 - General painting and site cleanup.
- painted support posts on top of bunker, patched up bunker roof, started painting West side.
 
 - X Reseal lysimeter w/ silocone.
- Also painted numbers on lysimeters.
 -  ! Begin design process for new lysimeters.
- Pondering hardy-backer, concrete, stone/tile
 
 - New covers, may not be needed depending on new design, ponder tarps.
 
 
IT Tech Stuff:
- DONE: Netgear switch (mtc)
- Would be nice to have a 16-24 port silent gig switch.
 
 - Inventory of items for calibration/overhaul.
 - Replace Win VM? (mtc)
 - Spare linksys wireless/firewall? (mtc)
- Bring one up this fall or whenever from UCSB.
 
 - Network overhaul with VPN?
- No, not really needed.
 
 - Fix the frigging PST/PDT issue on the Mac. (mtc)
 
Programming/scripting/processing
- (mtc) LiDAR error checking.
 - (Dave+Adam/mtc) LiDAR auto processing.
 - (Ned/mtc) Realtime MASC filter & display?
 - X (mtc) reprogram data schlepping to put ".dat" at end of file names.